Israel's Transportation Ministry is expected to announce the suspension of Jerusalem's light rail train for a period of approximately one week, Walla! reported.
According to the report, the suspension will take place at the end of January. During the five-day period, the trains will appear to operate as usual, but will not transport passengers, instead testing the new operating system installed by the operator, Kfir, along the entire length of the line, from Neve Yaakov to Hadassah Ein Kerem Medical Center.
Following this test period, the light rail will operate for the first time along its entire length, and the "red" line will officially increase in length from 14 kilometers to 22 kilometers, and from 23 stations to 35 stations.
The extended route was scheduled to begin operating approximately two years ago, but was delayed for a number of reasons, including that some of the testing staff, who were from Europe, left Israel in the period following the October 7 massacre.... Read More: Arutz-7